The inspection cycle should be determined according to the actual conditions of the equipment.
The minor repair cycle is conducted every half month to one month and includes:
(1) Check the bowl tile;
(2) Check the wear of the taper sleeve and the straight sleeve and check the gap.
(3) Check the meshing clearance of the bevel gear;
(4) Check the transmission bushing clearance;
(5) Check the hydraulic device (if the hydraulic device is not equipped) and the lubricating device or replace the lubricating oil;
(6) Cleaning of main parts.
The medium repair period is about 4 to 6 months, and its main contents include:
(1) Replace the liner;
(2) repair or replace the eccentric bushing, taper sleeve and straight sleeve;
(3) repair or replace the bowl tile and dustproof device;
(4) Repair or replace the bevel gear, drive shaft and bearing bush;
(5) repairing the adjustment ring and the support sleeve thread;
(6) Carry out all inspections and treatments of minor repair projects;
(7) Decompose the motor, blow dust and descaling and check the bearing bushing of each part; decompose the oil switch, clean and deal with the defects; electrical adjustment and test of each part; check and repair the switchboard and other cable lines.
The overhaul is about four years or based on actual conditions. Its contents include:
(1) repair or replace the rack and the basic part of the problem;
(2) Carry out all inspections and treatments of the intermediate repair project, as well as carry out technical transformation;
(3) Replace the stator coil of the motor (determined according to the preventive test) and dip the paint; determine whether to replace the rotor shaft according to the actual situation.Ultrasonic Welding Machine,Ultrasonic Welder,Sonic Welder,Handheld Ultrasonic Welder
Changzhou Piling Automation Technology Co., Ltd. , https://www.plultrasonicmould.com